11 October 2019 | Story Valentino Ndaba | Photo Johan Roux
JN Boshoff Memorial lecture
From left: Prof Hendri Kroukamp (Dean of the Faculty of Economic and Management Science), Prof Puleng LenkaBula (Vice-Rector: Institutional Change, Student Affairs, and Community Engagement), Kimi Makwetu (Auditor-General South Africa), and Dr Lyndon du Plessis (Head of the Department of Public Administration and Management).

It is reported R390 billion in irregular expenditure has been accumulated over the past 10 years since the 2008-09 financial year. Local government has experienced an upward trend from R3 billion to R21 billion, while an increase from R1 billion to R51 billion has been seen at provincial government level.

Fixing the crisis 

South Africa’s global credit quality has deteriorated as a result of poor financial performance.  This is evidenced by the numerous downgrades from Moody’s over the past few years. The Auditor-General Kimi Makwetu proposes that accountability has the potential to resolve the issue.

Makwetu presented this year’s JN Boshoff Memorial Lecture titled: Accountability as a basis for service delivery and economic growth at the University of the Free State’s Bloemfontein Campus on Wednesday 9 October 2019. 

“The whole idea of accountability as a basis for service delivery and economic growth is a pursuit that needs to be tackled from different angles because auditors are not going to succeed if the tone at the top in the institutions is not at the right place.”

Auditing irregularities remain a cause for concern 
The Auditor-General referred to auditing irregularities as an imbalance between people, money, and material. He alluded to the need to “narrow the space for the abuse of public resources” by escalating the level of preventive controls so that materials are paid for and delivered. The Amendment Act becomes instrumental in achieving this.

President Cyril Ramaphosa proclaimed 1 April 2019 as the official commencement date of the Public Audit Amendment Act (Act No. 5 of 2018) which introduced new mechanisms to ensure that audit findings are properly addressed and recommendations are implemented.  The Act is a tool to root out material irregularities such as fraud, theft, non-compliance with or contravention of legislation, or a breach of a fiduciary duty.

Expanding the scope of auditors

The Act empowers auditors to enforce accountability in the form of referring irregularities to public bodies for further investigation, recommending binding remedial actions, and issuing certificates of debt.

According to Makwetu accountability means that citizens’ rights to service delivery are respected. “Improved accountability speaks directly to the government’s ability to appropriately manage public resources to the benefit of the citizens they serve. It created a solid foundation for service delivery to take place and for the citizens to tangibly experience and feel the vision set by the constitution.” 

For service delivery and economic growth to manifest, accountability in the public sector needs to become second nature. The role of auditors in ensuring this shift is therefore of utmost importance.

News Archive

Power shortage: Measures to be implemented immediately
2008-01-31

1. In order to avoid the further implementation of power sharing, electricity companies countrywide are requiring, in addition to measures announced for domestic consumers, that major power consumers save a certain percentage of power.

2. Die UFS is one of the 100 largest clients of Centlec, the local electricity distribution company. During a meeting last Thursday evening with the 100 largest clients, it was indicated that the UFS had to deliver a saving of 10%. The details are as follows:

  • Provision is made to a certain extent for an increase in electricity consumption. The calculation is done as follows: maximum consumption for 2007+6%-10%.
  • This entails a saving during peak times, as well as a saving regarding the total number of units consumed.
  • The saving is calculated on a monthly basis.
  • Saving measures must be implemented immediately (from 7 March). If electricity-saving goals are not attained, power sharing will be resumed from 10 March.

3. The UFS has been controlling its peak demand by means of an energy control system for many years. The geysers of residences and certain central air-conditioning systems were linked to the control system in order to shift energy consumption to non-peak times.

4. In order to attain the goal of 10%, it is necessary to implement further energy control systems and additional measures – which requires time and money. Attention will have to be given, inter alia, to the following:

  • The 1000+ portable air-conditioning units on the campus (huge power guzzlers) must be connected to energy control appliances and systems.
  • All the filament bulbs must be replaced.

7. The UFS will be conducting high-level talks with Centlec later this week with a view to:

  • conveying the unique needs of the UFS in detail;
  • stating the impact of building and refurbishing projects that are currently in the implementation and planning phases;
  • requesting understanding for the fact that the UFS does not have the capacity to immediately deliver the 10% saving.
     

It is evident from discussions thus far that Centlec is sympathetic and wants to help, but also that immediate action and co-operation are expected from the UFS. During the meeting, the UFS must also report back on steps already taken (since 7 March) in this regard.

8. The installation of the emergency power units for the large lecture-hall complexes and a few other critical areas, which has already been approved, is continuing. About R3m is being spent on this. Additional emergency power needs reported to Physical Resources via line managers are currently being investigated with a view to obtaining a cost estimate and subsequently determining priorities in consultation with line managers.

It is recommended that:

a) All line managers, staff members and students be requested to give their full co-operation with regard to saving electricity in every possible way, and that current operational arrangements be amended if possible with a view to promoting power saving. 

Staff, students and other users of campus facilities be requested to see to it that lights and air conditioning (individual units) in unused areas are switched off.

b) The following measures drawn up in co-operation with electrical engineers come into effect immediately:

Arrangements to be made by Physical Resources staff:
(Additional capacity to be able to complete everything within a reasonable period of time will have to be found and funded. This aspect will be taken up with the line managers concerned):

  • The geysers of all office buildings will be switched off at the distribution board. Staff are requested to use a kettle for washing dishes, and are warned not to switch appliances on again themselves.
  • In all office buildings where 12V and 15W downlighters and uplighters remain switched on for decorative purposes and do not serve as primary illumination, the light switches will be disconnected.
  • Lighting in cloakrooms will be checked, and illumination levels will be reduced if possible.
  • All light armatures must be replaced by CFL types.
  • All lights on the grounds will be checked to ensure minimum power consumption.
  • The upper limit of all central cooling systems currently regulated via the energy control system must be set to 24 degrees.

Arrangements to be made by Kovsie Sport:

  • Sport activities requiring sports field illumination must be scheduled after 20:00 in the evening (the lights may not be on between 18:00 and 20:00.)
  • Sports field illumination must be managed so that such lights are not switched on unnecessarily.
     