Latest News Archive

Please select Category, Year, and then Month to display items
Previous Archive
04 August 2020 | Story Rulanzen Martin | Photo Supplied

 

Dr Nadine Lake, gender studies expert from the Centre for Gender and Africa Studies at the UFS, will participate in a streamed online Facebook discussion on ‘men and masculinities and finding ways of solving conflict and work towards healing the victims, the survivors, the perpetrators.’  This is the 13th episode of the #DigtallyYours discussion series initiated by the embassies of Sweden and the Kingdom of the Netherlands in SA, with support from the European Union in SA. The discussion will be moderated by renowned journalist, Redi Tlhabi.

Other panellists will include Mmatshilo Motsei, S’busiso Malope, Ruben Richards, and Xabiso Vili.

The discussion will be livestreamed on the Facebook page of the Embassy of Sweden as well as the Facebook page of the UFS on Wednesday 5 August 2020 from 15:00.

News Archive

How to interpret Centlec’s load shedding
2008-01-31

Everyone in South Africa is affected by power failures (load shedding). Centlec took certain measures to manage the situation. These measures are explained:

Time slots
See the following table for an indication of times when load shedding might be applied to specific areas:  http://www.centlec.co.za/power_shed/PDF/time_slots.pdf

Groups
The city was divided into six groups. This document clearly indicates which area in the city resorts under which group: http://www.centlec.co.za/power_shed/PDF/groups.pdf

According to the document, the university resorts under group 4. In the table with time slots it is the grey area.

Stages
Eskom developed three stages for load shedding. (See stage table at the bottom of the page http://www.centlec.co.za/power_shed/PDF/time_slots.pdf)
- Stage 1: Less load shedding is applied in stage 1. E.g. the UFS resorts in group 4 and on a Monday, according to stage 1, the power will not be switched off during 12:00 and 14:30 (this time slot is not highlighted in orange).
- Stage 2: More load shedding is applied in stage 2. Load shedding will be applied during stage 2 between 12:00 and 14:30 on a Monday at the UFS.
- Stage 3: All time slots are highlighted in orange, which indicates that power will be switched off for the whole duration of stage 3.

Example
Today, Tuesday, load shedding was scheduled to take place from 10:00 to 12:00 at the UFS. Currently, according to Centlec’s web site, stage 1 is active. This time slot is not marked in stage 1, therefore load shedding is not applied. Centlec gives also additional information; “No load shedding in progress.”

Keep in mind that if an area is at risk it does not automatically imply that the power will be switched off. It all depends on the request from Eskom at that particular moment whether the actual shedding is required.
 

We use cookies to make interactions with our websites and services easy and meaningful. To better understand how they are used, read more about the UFS cookie policy. By continuing to use this site you are giving us your consent to do this.

Accept