Latest News Archive

Please select Category, Year, and then Month to display items
Previous Archive
01 September 2020 | Story Nonsindiso Qwabe | Photo Supplied
Women
Carol Bouwer and Prof Puleng LenkaBula believe that the nation is constantly diverting to other issues that take the focus away from amplifying voices for the protection of women and children, hence no real change has taken place. Photo: Supplied

The intersectionality between politics, feminism, and social justice was unpacked extensively in the Student Affairs Women’s Month Webinar that took place on 25 August 2020. This was the second in a series initiated by the Qwaqwa Campus Student Affairs. Director of Student Affairs, Nicole Morris, said the webinars were initiated to encourage difficult conversations around womanhood in South Africa.

UFS Vice-Rector Institutional Change, Student Affairs, and Engaged Scholarship, Prof Puleng LenkaBula, and renowned businesswoman and media mogul, Carol Bouwer, were featured in the second instalment. Together they unpacked the dynamics of being a woman in modern-day South Africa in the face of the scourge of violence against women and children, as well as the transformation and greater representation of women in both positions and institutions of power.

 

Challenge the systems

Setting the tone, Prof LenkaBula said society as a collective needed to come together to challenge systems that oppress, mute, silence, and make it impossible for women to become dignified and contribute fully to the society we live in.

 “If we are to promote social justice, feminism, ethics, and gendered analysis, we have to ensure that we constantly challenge, rethink, and think again around issues that we feel are withholding women from being fully themselves.”

 Bouwer and Prof LenkaBula said the nation is constantly diverted to other issues that are shifting the focus from amplifying voices for the protection of women and children, hence no real change has taken place.

 “As someone who began working during the birth of our freedom in 1994, I think back to the elation that we felt at the creation of the constitution. There was so much jubilation about it, but we exported that excitement to the world and talked about what we had attained without practising it here.”

 “We continue to create systems and amazing documents as a nation, yet we do not implement the very things that will lead to a point where discussions such as these do not need to take place,” Bouwer said.

 Bouwer said the COVID-19 pandemic showed that South Africa had the necessary resources to prioritise gender-based violence, but those in power chose not to.

 “As we speak today, gender-based violence has become a national crisis. We talk about the intersectionality between politics, feminism, and social justice against the confluence of the opposite happening. With what happened when the COVID-19 pandemic was declared a national disaster, we’ve realised that we do have the wherewithal to mobilise for action in this nation, and it is the one thing we have not seen our leaders do,” she said.

 

Part-time feminism will not help

Prof LenkaBula said rethinking feminism was needed to move away from definitions of anti-manhood in order to promote feminist ideals that would benefit the nation as a whole.

 “As a feminist, I want to promote the idea that feminists are not promoting the defamation or marginalisation of men or stripping them of their dignity. We are saying that as men and women, no matter our gender or sexuality, we can work together to ensure that we all live with dignity, we all are equal, and we all express our talents, and are able to utilise opportunities that are available to us in fair ways.”

 Alluding to this, Bouwer said she hoped to see part-time feminism done away with in the rebuilding of society after the pandemic. “Coming out of this pandemic, may our feminism be transformed by everything that is currently happening. There is a huge injection of pathos happening right now and I hope that it is not a fad like everything else that has happened in South Africa, but that it becomes something that we really embody as we go back to whatever normal is going to look like,” she said.

 Qwaqwa Campus SRC Secretary General, Nelisiwe Masango, said the Division of Student Affairs planned the Women’s Month Webinars to discuss topics on issues that affect women directly.

 “These programmes are quite insightful and uplifting. They especially encourage young women to see that the revolution is there, it is real, and it is practical. It gives meaning to continue advocating for better and safe spaces for women. Many times, spaces of contestation are male dominated and therefore women have to be empowered to contest these spaces. These engagements must be ongoing or continuous so that we all understand the issues we are affected by and advocate for a better society.”

News Archive

Power interruptions: Information for internal communication
2008-01-31

As part of the UFS’s commitment to address load shedding, the management would like to communicate the following:

The UFS mainly deals with the power interruptions by way of (a) the possible installation of equipment (e.g. generators) and (b) operational arrangements to ensure the functioning of the UFS in spite of power interruptions.

During the past week progress was made on both fronts. The information that follows resulted from a meeting of a task team of Physical Resources led by Mr Nico Janse van Rensburg, which took place on Monday 28 January (this task team naturally focuses on physical solutions) and a discussion by Exco on Wednesday 30 January 2008. Exco discussed the recommendations of the mentioned task team in respect of physical aspects, as well as the operational arrangements proposed by faculties.

Physical solutions

A Main Campus

1. New emergency power installations already approved:

Last week Exco gave its approval for the design and installation of emergency power equipment in all the large lecture-hall complexes to proceed immediately.

In all these cases

  • load surveys have been completed and a start has been made with the ordering of equipment and the process of appointing contractors. (Exco approved the adjustment of normal tender procedures in an attempt to expedite completion.)
  • generators with 20-30% more capacity than required for the current load are being ordered.
  • provision is being made for the connection of lights and at least one wall plug to the emergency power.
  • the expected construction time is 16 weeks (except in the case of the Flippie Groenewoud Building where it is 6 weeks).

The above-mentioned concerns lecture halls/ venues in the following buildings: Examination Centre, Flippie Groenewoud Building, Stabilis, Genmin and the Agriculture Building.

As far as the Agriculture Building is concerned, a larger generator (larger than required for lecture venues only) is being ordered in view of simultaneously providing essential research equipment (refrigerators, ovens, glasshouses) with emergency power within 16 weeks.

2. Investigation into the optimal utilisation of present emergency power installations

All the emergency power systems are being investigated on the basis of a list compiled in 2006 to determine whether excess capacity is available and whether it is possible to connect additional essential equipment or lights to it.

The electrical engineer warns as follows:
“Staff members must under no circumstances overload present emergency power points.

A typical example of this is a laboratory with 10 power points of which 2 points are emergency power outlets. Normally a fridge and freezer would, for example, be plugged into the two emergency power points, but now, with long load-shedding interruptions, a considerably larger number of appliances are being plugged into the power point by means of multi-sockets and extension cords. In the end the effect of such connections will accumulate at the emergency generator, which will then create a greater danger of it being overloaded and tripping, in other words, no emergency power will then be available.”

3. Requests and needs addressed directly to Physical Resources or reported to Exco via the line managers.

All the physical needs and requests addressed directly to Physical Resources or submitted to Exco via the line managers are being listed, classified and considered technically in view of their being discussed by the task team on Monday 11 February.
The information will (a) lead to recommendations to Exco regarding possible additional urgent emergency power installations, and (b) be used in the comprehensive investigation into the UFS’s preparedness for and management of long power interruptions.

Requests that can easily be complied with immediately and that fit into the general strategy will indeed be dealt with as soon as possible.

4. Purchase of loose-standing equipment: light, small, loose-standing generators, UPSs as solutions to/ aids during power interruptions

Exco approved that

a) faculties and support services accept responsibility themselves for the funding and purchase of loose equipment such as, for example battery lights, should they regard these as essential.
b) UPSs (uninterruptible power supplies) that faculties and support services wish to purchase to combat the detrimental effect of unexpected power interruptions on computer equipment) can (as at present) be purchased from own funds via Computer Services.
c) UPSs (uninterruptible power supplies) that faculties and support services wish to purchase to combat the detrimental effect of unexpected power interruptions on other types of equipment can normally be purchased from own funds with the consent of the line manager concerned.
Note: Please just make sure of the appropriateness of the equipment for a specific situation: it is not a power supply that can bridge a two-hour power interruption.)
d) small, loose-standing generators can be purchased from own funds via Physical Resources and installed under their supervision.
e) laptop computers can , where necessary, be purchased from own budgets. The availability of second-hand laptop computers must be taken into account.

B Vista

No major problems have been reported to date. The situation is being monitored and will be managed according to need. The same guidelines that apply to the Main Campus will naturally also apply to the Vista Campus.

C Qwaqwa

The situation is receiving attentions and solutions have already been found for most problems.

D General

1. All-inclusive project
A comprehensive investigation into the UFS’s preparedness for and management of long power interruptions will be launched as soon as possible. Available capacity will be utilised first to alleviate the immediate need. The needs assessment to which all faculties and support services have already contributed is already an important building block of the larger project.

2. Building and construction projects currently in the planning and implementation phase
The need for emergency power for projects such as the new Computer Laboratory is being investigated proactively and will be addressed in a suitable manner.

3. Liaison with Centlec
Attempts at direct and continuous liaison are continuing in an attempt to accommodate the unique needs of the UFS.

4. HESA meeting and liaison with other universities
A representative of the UFS will attend a meeting of all higher education institutions on 11 February. The meeting is being arranged by HESA (Higher Education South Africa) to discuss the implications for the sector, the management of risks and the sector’s response to government.

5. Internal communication
It is the intention to communicate internally after every meeting of the task team, which will take place on Mondays. Strategic Communication will assist in this regard.


 