30 June 2021 | Story André Damons | Photo André Damons
Dr Nicholas Pearce, Head of the COVID-19 Task Team at the Universitas Academic Hospital, leads a dedicated team of professionals at the testing and vaccination site of the Universitas Academic Hospital, adjacent to our Bloemfontein Campus.

It is impossible to quantify the number of hours Dr Nicholas Pearce, Head of the COVID-19 Task Team for the Universitas Academic Hospital, spent working in response to this deadly virus since the first case was reported in South Africa last year. 

According to Dr Pearce, who is the Head of the Department of General Surgery in the Faculty of Health Sciences at the University of the Free State (UFS), the initial preparation phase required many hours of brainstorming, planning, and physical hours working on site. He also spent countless hours awake at night trying to come up with solutions for the many challenges faced along the way. This is in addition to being available telephonically twenty-four-seven for any issues related to equipment, staffing, and facilities.

“I was attending a vascular surgery congress in Germany last year January (2020) when China just announced the outbreak of COVID-19. I noticed an increased number of travellers wearing surgical masks at an airport in the Middle East when I was travelling to South Africa. 

“Upon my return to work, I approached management to discuss procurement of PPEs, as it was just a matter of time before COVID-19 would hit South Africa and the rest of the world. When things escalated, I was asked to head the COVID-19 response team at Universitas Hospital,” explains Dr Pearce.

Kind human being with a soft heart

(Photo: André Damons)

Dr Pearce, who was brought up to always strive to be better, is driven and motivated to succeed. He has a very analytical brain and loves challenges. In fact, he does not believe in problems and only sees challenges. This kind human being can sometimes seem quite tough on the outside, but actually has a very soft heart. 

“I think it is human nature to want to feel needed. I have an inherent urge to help my fellow human beings. This is also the reason why I became a health-care professional and why I am passionate about teaching,” says Dr Pearce. 

With South Africa lagging behind with its vaccination programme, the hard work is far from over for Dr Pearce and his team. Says Dr Pearce: “The initiation of a mass vaccination site posed a whole new set of challenges, which once again required many hours of planning. The initial stages of running the vaccination site required many hours of physical hard work a day. Then there is also the daily operations meeting at 18:00 every weekday to discuss the vaccine roll-out in the province.”

Frustrations and setbacks

For Dr Pearce, this pandemic highlighted the differences between individuals from different social classes in our country. Providing quarantine and self-isolation facilities for individuals who do not have access to such facilities at home is one such example. 

“We all have a right to clean water and good quality healthcare. This also includes a right to oxygen. This right to oxygen has proved to be one of our great challenges in managing this pandemic. Delivery of these large amounts of oxygen has been especially challenging. Some days we require in excess of five tons of oxygen,” says Dr Pearce. 

(Photo: André Damons)


There have been many frustrations and setbacks on this journey, some of which can be quite demoralising and demotivating, but knowing that he is doing something good for his fellow human beings gives this gentle and diligent healthcare worker a tremendous amount of energy. “Positive feedback from patients and colleagues far outshines all the frustrations and disappointments,” concludes Dr Pearce. 


Outside of work

After finishing online meetings at home, Dr Pearce relaxes with his partner by chatting about the day’s events and cooking supper together while enjoying a glass of wine. He also tries to connect with family who lives in Gauteng. Because of work pressures and the pandemic, he has not been able to see them as much. 

News Archive

UFS keeps the power on
2015-06-24

 

At a recent Emergency Power Indaba held on the Bloemfontein Campus, support structures at the university met to discuss the Business Continuity Intervention Plan to manage load shedding on the three campuses of the UFS.

Currently, 35 generators serving 55 of the buildings have already been installed as a back-up power supply on the three campuses of the university. According to Anton Calitz, Electrical Engineer at the UFS, the running cost to produce a kWh of electricity with a diesel generator amounts to approximately three times the cost at which the UFS buys electricity from Centlec.

Planned additional generators will attract in excess of R4 million in operating costs per year. For 2015, the UFS senior leadership approved R11 million, spread over the three campuses. Remaining requirements will be spread out over the next three years. University Estates is also looking at renewable energy sources.

On the Bloemfontein Campus, 26 generators serving forty-one buildings are in operation. On South Campus, two generators were installed at the new Education Building and at the ICT Server Room. Lecture halls, the Arena, the Administration Building, and the library will be added later in 2015. Eight generators serving 12 buildings are in operation on the Qwaqwa Campus. In 2015, the Humanities Building, Lecture Halls and the heat pump room will also be equipped with generators.

Most buildings will be supplied only with partial emergency power. In rare cases, entire buildings will be supplied because the cost of connecting is lower than re-wiring for partial demand. According to Nico Janse van Rensburg, Senior Director at University Estates, emergency power will be limited to lighting and power points only. No allowances will be made for air-conditioning.

“Most area lighting will also be connected to emergency power,” he said.

Where spare capacity is available on existing emergency power generators, requests received for additional connections will be added, where possible, within the guidelines. The following spaces will receive preference:
- Lecture halls with the lights, data projectors, and computers running
- Laboratories for practical academic work and sensitive research projects
- Academic research equipment that is sensitive to interruptions
- Buildings hosting regular events

According to Janse van Rensburg, all further needs will be investigated. Staff can forward all emergency power supply needs to Anton Calitz at calitzja@ufs.ac.za

Staff and students can also manage load shedding in the following ways:

1. Carry a small torch with you at all times, in case you are on a stairwell or other dark area when the lights go out. You can also use the flashlight app on your phone. Download it before any load shedding occurs. This can come in handy if the lights go out suddenly, and you cannot find a flashlight. Load-shedding after dark imposes even more pressure on our Campus Security staff. We can assist them with our vigilance and preparedness by carrying portable lights with us at all times and by assisting colleagues.
2. Candles pose a serious safety risk. Rather use battery- or solar-powered lights during load shedding.
3. Ensure that your vehicle always has fuel in the tank, because petrol stations cannot pump fuel during power outages.
4. Ensure that you have enough cash, because ATMs cannot operate without electricity.
5. The UFS Sasol Library has study venues available which students can use during load shedding.
6. When arranging events which are highly dependent on power supply, especially at night, organisers should consult the load-shedding schedule before determining dates and preferably also make back-up arrangements. If generators are a necessity, the financial impact should be taken into consideration.

The senior leadership also approved a list of buildings to be equipped with emergency power supplies.

More about load shedding at the UFS:
Getting out of the dark
More information, guidelines and contact information

 

 

We use cookies to make interactions with our websites and services easy and meaningful. To better understand how they are used, read more about the UFS cookie policy. By continuing to use this site you are giving us your consent to do this.

Accept