06 September 2021 | Story Leonie Bolleurs | Photo Mpendulo Myeni
Lucien le Grange, architect and urbanist, delivered the 32nd Sophia Gray Lecture this year. The online event was hosted in the Oliewenhuis Art Museum, where an exhibition of his work was also on display.

The Department of Architecture at the University of the Free State (UFS) presented the 32nd Sophia Gray Memorial lecture at the Oliewenhuis Art Museum on 26 August 2021.

The speaker at this year’s event – presented online – was Lucien le Grange of Lucien le Grange Architects and Urban Planners. Some of his work includes the Nelson Mandela Gateway to Robben Island, the Prestwich Street Memorial, and the architecture and urbanism of District Six. 

Le Grange was part of the staff of the Cape Town School of Architecture from 1978 to 2011, where he taught Design and History and Theory of Architecture at undergraduate and postgraduate level. Most of his work was also conducted in the Western Cape.

Purposeful thinking and purposeful action

He believes a time such as this, marked by so many environmental and public health challenges, demands of us purposeful thinking and purposeful action. “The recent social disruption in our country specifically requires honest reflection of the kind of social system we seek to create for ourselves as a nation.”

“We are at a crossroads that gives us an opportunity to seriously and honestly confront our shortcomings as a society. We need to find ways to restore confidence in ourselves and to fashion a new national urban development strategy,” he continues.

Le Grange is of the opinion that the social unrest in July is important for architects and urban designers to reflect upon. He elaborates: “In different ways, the sight of unrest stretching from Phoenix to Soweto shows that the apartheid city format remains very much intact. There has in fact been very little reconstruction and development. Our cities remain unsustainable, inequitable, and inefficient. These spaces are still conglomerations where there is no choice, no sense of place, no sense of safety, and no sense of security.”

For him as an architect and urbanist, the images of freeway landscapes summarise much of the shortcomings of our South African cities. He feels that it demonstrates a dependency on the private motor vehicle at the expense of safe and secure public transport. “It illustrates an environment full of physical barriers, which segregates communities in the isolated, monofunctional informal settlements that populate our urban landscapes,” he says. 

Le Grange is convinced that this condition – all over our nation’s towns and cities – is an inditement against our dysfunctional state. “It is astounding that 27 years since the birth of our democracy, the apartheid city planning model still prevails,” he says. 

Projects contributing to the social fabric

Much of the work he displayed during the lecture was done in the first decade after 1994. He says in the early years of our new democracy, the aspirations and ambitions of the RDP somehow influenced how our social services programmes were conceived and how they were delivered. The projects were executed in a manner that allowed greater social interpretation in terms of its design and execution. Facilities were expected to serve a broader social role, and its construction very often incorporated training and employment opportunities. 

“It was an exciting time, although short-lived.”

He grouped his work into three overlapping areas of concern – architecture and the city, architecture and history, and architecture and community – which have informed the understanding of various contextual challenges and inspired his design ideas. 

“These areas have assisted us to develop strategies that assist city building, urban design, engagement with user communities, the making of buildings, and the treatment and use of building materials,” he says. 

Talking about architecture and the city, he discussed the urban design for the old Klipfontein Road Corridor. The project consists of an activity corridor along 35 km of landscape and is envisioned as a space that will allow for various development opportunities. The project also aims to break down the barriers that divide much of the urban landscape in Cape Town and to populate it with nodes, coinciding with activity areas such as a stadium, schools, or shopping malls.

Le Grange’s portfolio also includes projects that investigate a revitalisation of destroyed and forgotten sites or landscapes in District Six.

As an urbanist, he investigates how cityscapes should perform to retain integrity and a kind of density that allows mixed-use development. He points out some of the opportunities that come with dense urban living, offered by structures such as major routes, punctuated with urban landmarks and streets. Multi-purpose in their function, he believes streets are social spaces where children can play and where communities can gather during a carnival or a protest. “It is also a place of finer intimacies, from which to be seen and into which one can look onto,” he adds. 

“One must also remember the existence of natural features; in this case the presence of Table Mountain that is like a mantle wrapped around Cape Town,” says Le Grange.

The declaration of the Group Areas Act in 1966 meant the end of this vibrant and highly liveable quarter in the city, and was followed by a period of destruction, implemented between the mid-1970s through to the 1990s.

Le Grange says there was, however, not a full removal. Places of worship and the schools were still occupied. When requested to develop a first-phase housing development for people to return to this area, it was around these particular social spaces that he worked. 

The first nine houses built for this project were privately funded by the developers and were constructed without any approval from the authorities. The occupants of these houses were the first claimants to be moved back to District Six after being forcibly removed by the apartheid regime. 

The Klipfontein and District Six projects are but two on the list of projects in which Le Grange – who believes all of humanity has a right to a life of dignity – was involved to better the lives of communities around him. 

Other projects he touched on during his lecture include the Genadendal Heritage, Conservation, and Restoration project, the Ocean View Community Hall, and the Hanover Park Market. 

View the complete lecture and access the virtual exhibition here. A live exhibition is also on display in the Oliewenhuis Art Museum. 

News Archive

Power interruptions: Information for internal communication
2008-01-31

As part of the UFS’s commitment to address load shedding, the management would like to communicate the following:

The UFS mainly deals with the power interruptions by way of (a) the possible installation of equipment (e.g. generators) and (b) operational arrangements to ensure the functioning of the UFS in spite of power interruptions.

During the past week progress was made on both fronts. The information that follows resulted from a meeting of a task team of Physical Resources led by Mr Nico Janse van Rensburg, which took place on Monday 28 January (this task team naturally focuses on physical solutions) and a discussion by Exco on Wednesday 30 January 2008. Exco discussed the recommendations of the mentioned task team in respect of physical aspects, as well as the operational arrangements proposed by faculties.

Physical solutions

A Main Campus

1. New emergency power installations already approved:

Last week Exco gave its approval for the design and installation of emergency power equipment in all the large lecture-hall complexes to proceed immediately.

In all these cases

  • load surveys have been completed and a start has been made with the ordering of equipment and the process of appointing contractors. (Exco approved the adjustment of normal tender procedures in an attempt to expedite completion.)
  • generators with 20-30% more capacity than required for the current load are being ordered.
  • provision is being made for the connection of lights and at least one wall plug to the emergency power.
  • the expected construction time is 16 weeks (except in the case of the Flippie Groenewoud Building where it is 6 weeks).

The above-mentioned concerns lecture halls/ venues in the following buildings: Examination Centre, Flippie Groenewoud Building, Stabilis, Genmin and the Agriculture Building.

As far as the Agriculture Building is concerned, a larger generator (larger than required for lecture venues only) is being ordered in view of simultaneously providing essential research equipment (refrigerators, ovens, glasshouses) with emergency power within 16 weeks.

2. Investigation into the optimal utilisation of present emergency power installations

All the emergency power systems are being investigated on the basis of a list compiled in 2006 to determine whether excess capacity is available and whether it is possible to connect additional essential equipment or lights to it.

The electrical engineer warns as follows:
“Staff members must under no circumstances overload present emergency power points.

A typical example of this is a laboratory with 10 power points of which 2 points are emergency power outlets. Normally a fridge and freezer would, for example, be plugged into the two emergency power points, but now, with long load-shedding interruptions, a considerably larger number of appliances are being plugged into the power point by means of multi-sockets and extension cords. In the end the effect of such connections will accumulate at the emergency generator, which will then create a greater danger of it being overloaded and tripping, in other words, no emergency power will then be available.”

3. Requests and needs addressed directly to Physical Resources or reported to Exco via the line managers.

All the physical needs and requests addressed directly to Physical Resources or submitted to Exco via the line managers are being listed, classified and considered technically in view of their being discussed by the task team on Monday 11 February.
The information will (a) lead to recommendations to Exco regarding possible additional urgent emergency power installations, and (b) be used in the comprehensive investigation into the UFS’s preparedness for and management of long power interruptions.

Requests that can easily be complied with immediately and that fit into the general strategy will indeed be dealt with as soon as possible.

4. Purchase of loose-standing equipment: light, small, loose-standing generators, UPSs as solutions to/ aids during power interruptions

Exco approved that

a) faculties and support services accept responsibility themselves for the funding and purchase of loose equipment such as, for example battery lights, should they regard these as essential.
b) UPSs (uninterruptible power supplies) that faculties and support services wish to purchase to combat the detrimental effect of unexpected power interruptions on computer equipment) can (as at present) be purchased from own funds via Computer Services.
c) UPSs (uninterruptible power supplies) that faculties and support services wish to purchase to combat the detrimental effect of unexpected power interruptions on other types of equipment can normally be purchased from own funds with the consent of the line manager concerned.
Note: Please just make sure of the appropriateness of the equipment for a specific situation: it is not a power supply that can bridge a two-hour power interruption.)
d) small, loose-standing generators can be purchased from own funds via Physical Resources and installed under their supervision.
e) laptop computers can , where necessary, be purchased from own budgets. The availability of second-hand laptop computers must be taken into account.

B Vista

No major problems have been reported to date. The situation is being monitored and will be managed according to need. The same guidelines that apply to the Main Campus will naturally also apply to the Vista Campus.

C Qwaqwa

The situation is receiving attentions and solutions have already been found for most problems.

D General

1. All-inclusive project
A comprehensive investigation into the UFS’s preparedness for and management of long power interruptions will be launched as soon as possible. Available capacity will be utilised first to alleviate the immediate need. The needs assessment to which all faculties and support services have already contributed is already an important building block of the larger project.

2. Building and construction projects currently in the planning and implementation phase
The need for emergency power for projects such as the new Computer Laboratory is being investigated proactively and will be addressed in a suitable manner.

3. Liaison with Centlec
Attempts at direct and continuous liaison are continuing in an attempt to accommodate the unique needs of the UFS.

4. HESA meeting and liaison with other universities
A representative of the UFS will attend a meeting of all higher education institutions on 11 February. The meeting is being arranged by HESA (Higher Education South Africa) to discuss the implications for the sector, the management of risks and the sector’s response to government.

5. Internal communication
It is the intention to communicate internally after every meeting of the task team, which will take place on Mondays. Strategic Communication will assist in this regard.


 