21 September 2022 | Story Dr Olivia Kunguma. | Photo Supplied
Dr Olivia Kunguma
Dr Olivia Kunguma, left, and Dr Mmaphaka Tau from DiMTEC.

Opinion article by Dr Olivia Kunguma, Disaster Management Training and Education Centre for Africa, University of the Free State, and Dr Mmaphaka Tau, Managing Director: Resilience 4 Development Institute (Pty) Ltd.


On 11 September 2022 a tailings dam wall collapsed at the abandoned Jagersfontein diamond mine in the Free State’s Kopanong Local Municipality, unleashing a thick grey sludge. 

The mine is in the Xhariep District Municipality, which is home to about 5 800 people. Following the dam burst, more than 400 people were affected, 51 houses were destroyed, and critical infrastructure was affected. 

The dam burst at the mine, which was established in the 1800s and to date has been owned by several mine moguls, led to serious devastation in the community. Within hours of the event the media had already dubbed it the “Jagersfontein disaster”. 

But the media cannot loosely report it as a “disaster”. It is not the appropriate classification according to the Disaster Management Act. There is a need for governing institutions and their legislation to be respected and recognised, as this will improve on governance. South Africa has good policies, but implementation is, in certain areas, lacking. Hereunder, we note that there is inappropriate use of terminology, which depicts the inadequate understanding of the disaster risk management function.

What is a disaster?

The DMA defines a “disaster” as a progressive, sudden, widespread, natural, or man-made occurrence that causes or threatens to cause death, disease or injury, damage to the environment, and disruption of life. According to the Act, it is of a magnitude that “exceeds the ability of those affected by the disaster to cope with its effects using only their resources”. At the international level, the United Nations International Strategy for Disaster Reduction (UNISDR) developed a terminology guide that aims to promote a common understanding and usage of disaster management concepts. It assists the authorities and the public (in this case, by “public” we refer mainly to the media) in educating the populace.

For the dam burst to be termed a “disaster”, several steps must be adhered to within South African jurisprudence: 

The National Disaster Management Centre (NDMC) must first assess the magnitude and severity of the event, and then classify it as a local, provincial, or national disaster. This assessment also considers the provisions of Section 2 (1)(b) of the DMA, stating that the Act does not apply to an occurrence that can be dealt with in terms of other legislation. The rationale of the above is that the National Disaster Management Framework of 2005 (NDMF) provides that disaster management plans must be developed by relevant organs of states and other entities, who are the custodians of certain hazards or activities to manage disaster risks in their areas of legislative responsibility. For example, mining-related activities are the responsibility of the Department of Mineral Resources and Energy. This department’s mission is clear: to regulate, transform and promote the mineral and energy sectors. 

Since the event or incident occurred in a local sphere of government (Kopanong Local Municipality), it can then be classified as a local disaster subject to the satisfaction of the provisions of Section 2(1)(b). According to Section 23(4) of the DMA, an event can be classified as a “local disaster” if it affects a single local metropole, district, or municipality, and that entity can deal with the event effectively. The district municipality and the local municipality are responsible for the coordination and management of the local disaster. 

If the event has not been declared as a local state of disaster, other existing legislation, contingency arrangements, or by-laws can guide the management of the event in line with the appropriate contingency arrangements. Other government spheres and state organs can still assist with the management of the event in line with the applicable disaster risk management plans called for under the National Disaster Management Frameworks. 


Dr Mmaphaka Tau 

Of critical importance and aligned to the thrust of the District Development Model is the provision of Section 54 (4) of the DMA, which asserts that “irrespective of whether a local state of disaster has been declared in terms of section 55, a national or provincial organ of state, or another municipality or municipal organs of state are not precluded from providing assistance to a municipality to deal with a local disaster and its consequences”. 

In the same way, and on the strength of section 23 of the DMA, suppose the event has been classified as a local disaster: there are added benefits to dealing with the occurrence, especially in the face of a lack of robust disaster risk management plans and the dearth of disaster risk management implementation capacity both for coordination (by Disaster Management Centres) and mainstreaming (by relevant organs of state and other entities). In that case, the municipal council may declare a local state of disaster by notice in the provincial gazette (See Section 55 of the DMA).

The disaster declaration will then provide for measures such as, but not limited to:
• Available resources such as facilities, vehicles, and funding are released; 
• Personnel of the organs of the state are released to render emergency services; 
• Evacuation of the affected population to temporary shelters;
• The regulation of movement;
• The dissemination of information; 
• The maintenance and/or installation of temporary lines of communication; and 
• The suspension of or limiting of alcohol in disaster-stricken areas.
Therefore, until all the above processes have been followed, the Jagersfontein dam burst can only be termed a “disaster” without the ability to apply the above measures.

Who is responsible, and how can we move forward?

Jagersfontein Developments (Pty) Ltd owns the mine, implying that it should be their primary responsibility, as the asset owner, to actively contribute to the management of the occurrence of an incident. Even the Minister of Mineral Resources and Energy, Gwede Mantashe, rightfully stated that the responsibility of compensating affected individuals would be placed on the mine owners. According to the Mine Health and Safety Act 29 of 1996 and its regulations, “the employer must take reasonable measures to ensure that no person is injured as a result of the failure of any dam wall”. It was reported that the company was warned of the tailings exceeding the authorised waste volumes. But the company did not attend to the warning. It is also assumed that the company is aware of the policies, legislation and standards they should adhere to, such as the Global Industry Standard on Tailings Management (GISTM), which strives to achieve the goals of zero harm to people and the environment, mine safety, and to mitigate catastrophic failure through tailings management. Fortunately, the company has taken full responsibility and has accepted liability. They have also refrained from calling Jagersfontein a ‘mine’, opting to call it a “processing facility”. Perhaps this also has legal implications. 

Nonetheless, besides the company taking full responsibility, the government must also play its part and make sure that policies, legislation, standards, etc. are implemented, and that there is full compliance. 
They cannot wait for a catastrophic event to occur and then start pointing fingers. This scenario calls for an embracing of the principles and practices of risk-informed development, which calls for an understanding of development that considers multi-faceted, dynamic, interdependent, transboundary, simultaneous, and systemic risks. It thus describes a shift in mindset – across sectors and stakeholders – from managing single hazards to incorporating existing and future risks in all development processes from the outset, and therefore choosing development pathways that prevent the creation of risks. The Jagersfontein case study is a classic case of an ignored Risk Informed Development (RID) approach, which is gravely regrettable.

The limited understanding of the various stakeholders’ roles and responsibilities, and the misinterpretation of important terminology, call for robust capacity development programmes driven by the National Disaster Management Centre in collaboration with Provincial and Municipal Disaster Management Centres. There is also a palpable need for a firm implementation of Priority 1 (Understanding Disaster Risk) of the Sendai Framework for Disaster Risk Reduction 2015-2030 (SFDRR), which states that policies and practices for disaster management should be based on an understanding of risks in all dimensions of vulnerability, capacity, exposure of persons and assets, hazard characteristics, and the environment. 

News Archive

State of our campuses: UFS closes campuses until Friday 28 October 2016 to readjust academic programme
2016-10-15

UFS announces strategy for completion of the 2016 academic year

Agreement between UFS management and student leadership in relation to residences

After almost four weeks of student protests about fees at the University of the Free State (UFS) and the subsequent suspension of the academic programme and closing of campuses, the senior leadership announced on 14 October 2016 a strategy to ensure that students will be able to complete the 2016 academic year.

The university on 13 October 2016 announced that it will shut down its Bloemfontein and South Campuses until 28 October 2016 for crucial and complex arrangements to be put in place to readjust the academic calendar and ensure that all students can complete their studies. The senior leadership did, however, make it clear that the university will not be shutting down for the remainder of 2016.

No teaching and learning activities at undergraduate and honours level will be offered between 17 October and 28 October 2016. The university will re-start teaching and learning at undergraduate and honours level in the first week of November 2016.

However, teaching and learning will not take place in the classrooms during November 2016, but through a different mode of delivery that consists of a combination of printed and recorded lectures, study materials and learning aids that will be provided by the university and delivered through Blackboard. In this manner no attempts at disrupting the rest of the academic year will affect our students’ academic programme. Students, however, will sit for the exam on campus.

Students in residence accommodation can return to campus as from 29 October 2016 and it is recommended that students who do not have off-campus internet access return to campus in order to access study material to complete the academic year.A new timetable for exams is still being developed and will be communicated as soon as the arrangements have been finalised.

Faculties have been differently affected by the loss of teaching time. Some faculties like the Faculty of Law have completed their curriculum, while other faculties like the Faculty of Natural and Agricultural Sciences require more teaching time. Some faculties, like the Faculty of Health Sciences, cannot do teaching through alternative modes of delivery.

The needs of the different faculties have been taken into account for developing a rescue plan to complete the 2016 academic year.

  • The Faculty of Health Sciences will continue its classes and clinical rotations as normal for all three schools on the Bloemfontein Campus and in the relevant hospitals. All students registered in programmes in the Faculty of Health Sciences will stay in residences for the full period of their studies and exams. Final-year medical students will graduate in December 2016 as expected.
  • In the Faculty of Economic and Management Sciences, final-year students for the Certificate in the Theory of Accounting (CTA) will stay on campus during October through to December 2016 and their classes and tests will not change.
  • Arrangements for all other faculties and programmes are being prepared and within the next week, students and parents/guardians will receive communication about how curriculum content will be completed and when the final exams will take place.
  • The university is extending the academic year so that we can recuperate all the lost teaching and learning time. The qualifications conferred on the 2016 class will be of the same quality and standards as all UFS qualifications.

The UFS is and will remain a fundamentally contact teaching and learning education university. However, under the current circumstances faced not only by the UFS, but higher-education institutions across the country, the best way of ensuring the integrity of the academic programmes in most faculties is by using an alternative way of teaching and learning. Other South African universities have chosen the same approach to be able to complete the academic year.

Instead of students going to class, they will have content delivered to them where they are (library, computer labs, their own computers, etc.) through Blackboard and printed and electronic material. This is a different way of learning but students will be carefully guided and supported.

Faculties are currently preparing all the necessary materials and instructions to support student learning.Standards and quality will be the same as if students were attending classes. Some faculties require practical laboratory work as part of their curriculum. The exam timetable will be adapted for these students to be able to complete their practical work when the academic activities commences in November 2016. The relevant faculties will communicate the schedule of practical work directly to the students.

Students in their final year will complete their studies during 2016. It is possible that in some cases the graduation ceremony for these students will be in June 2017 instead of April 2017. This will not prejudice students with bursaries, or committed employment in law firms or other businesses. The university will provide the necessary academic transcripts as proof of the completion of the relevant qualifications. None of these changes will affect postgraduate students.

The university will maintain regular communication with students and parents/guardians to update them on the new exams timetable.Faculties will communicate directly with students about issues related to their programmes.

“One of the areas in which significant progress was made, is that we were able to agree on a basis for stability with student leaders. The student protests occurred during an important time in the university’s academic calendar and the readjustment of our academic programme has put tremendous pressure on academic and support services staff, and created anxieties for parents,” said Prof Nicky Morgan, Acting Rector of the UFS.

“The senior leadership restates its commitment to free education as well as its willingness to stand together with students and other public universities to impress on government the urgency to decide on a time frame for the roll-out of free higher education for the poor and missing middle. We will use the next two weeks to meet with the leadership of Universities South Africa to coordinate collective action in this regard. We will furthermore also roll out a series of activities to inform and educate students and the general public on different models and experiences of providing free higher education,” he said.

The strategy to readjust the 2016 academic year is applicable to students on the Bloemfontein and South Campuses.


Released by:

Lacea Loader (Director: Communication and Brand Management)
Telephone: +27 51 401 2584 | +27 83 645 2454
Email: news@ufs.ac.za | loaderl@ufs.ac.za
Fax: +27 51 444 6393

 

State of our campuses #15: UFS closes campuses until Friday 28 October 2016 to readjust academic programme

State of our campuses #14: All academic activities on UFS campuses remain suspended on 13 and 14 October 2016

State of our campuses #13: Availability of information about plans for remainder of UFS 2016 calendar year

State of our campuses #12: All academic activities at UFS campuses suspended for 11 and 12 October 2016

State of our campuses #11: Academic activities on UFS campuses continue

State of our campuses #10: Impact of non-completion of the 2016 academic year on UFS students 

State of our campuses #9: Academic programme on all UFS campuses to resume on Monday 10 October 2016

State of our campuses #8:  UFS extends vacation as from 28 September until 7 October 2016, 28 September 2016

State of our campuses #7: All three UFS campuses will be closed today, 27 September 2016.

State of our campuses #6: All UFS campuses reopen on Tuesday 27 September 2016

State of our campuses #5: UFS campuses to remain closed on Monday 26 September 2016

State of our campuses #4: Decisions about the UFS academic calendar

State of our campuses #3: UFS campuses closed until Friday 23 September 2016 

State of our campuses #2: UFS Bloemfontein and South Campuses closed on Tuesday 20 September 2016 (19 September 2016)

State of our campuses #1: Academic activities suspended on UFS Bloemfontein Campus (19 September 2016)

 

We use cookies to make interactions with our websites and services easy and meaningful. To better understand how they are used, read more about the UFS cookie policy. By continuing to use this site you are giving us your consent to do this.

Accept