Latest News Archive

Please select Category, Year, and then Month to display items
Previous Archive
10 February 2025 Photo Supplied
Prof Theo Neethling
Prof Theo Neethling is from the Department of Political Studies and Governance at the University of the Free State.

Opinion article by Prof Theo Neethling, Department of Political Studies and Governance, University of the Free State.


In recent days, 14 South African soldiers have died in clashes with the Rwandan-backed M23 rebels in the eastern Democratic Republic of Congo (DRC). Several analysts argue that this marks a low point for the South African National Defence Force (SANDF) and that it is almost too late to implement the reforms needed to restore the military to an institution South Africans can once again take pride in. The incident recalls the so-called Battle of Bangui in March 2013 during the Central African Republic civil war — a major defeat for the SANDF that led to the Séléka rebels seizing control of the country.

This article aims to shed light on the challenges facing the South African military.

Following the historic transition of 1994, South Africa’s foreign policy shifted from a stance of conflict with its neighbours to one centred on regional relations built on the principles of common destiny, friendship, cooperation, and conflict resolution. The South African government sought to take on a leadership role on the continent, creating new opportunities for the SANDF as a military instrument.

Towards the end of the Mandela presidency, South Africa’s involvement in peace and security operations became a defining feature of its post-1994 foreign policy. The government demonstrated its firm commitment to regional stability by deploying the SANDF in peacekeeping operations — first in Lesotho in 1998, followed by the DRC in 1999 and Burundi in 2001.

Dwindling defence budget

However, since 1998 it became evident that the SANDF found it increasingly difficult to conduct operations as a declining budget started to constrain the SANDF. This is linked to the fact that between 1995 and 1998, the defence budget was cut by 11.1%, which eventually resulted in a growing mismatch between policy intent and execution. As a percentage of gross domestic product (GDP) South African defence spending had been reduced to less than 3% in the mid-1990s, which boiled down to less than 10% of total government spending. The defence budget then further decreased to 1.54% of GDP in 2004/05 and levelled out in 2014/15 at around 1.2% to 1.1% of GDP.

Despite a dwindling defence budget, the government increasingly expected the SANDF to support the SAPS as murder and death rates rose to levels comparable to — or in some cases even exceeding — those in high-intensity war zones internationally. This has placed the SANDF in an almost impossible position, forced to balance its demanding regional deployments with ongoing appeals from politicians and the public to intervene in crime-ridden hotspots where the SAPS is unable to fulfil its constitutional duty to protect South Africans.

Given these constraints and the changing global and regional geopolitical landscape in which the SANDF operated, the government appointed a task team to draft a second defence review, following the South African Defence Review of 1998, which was finally published as the 2015 South African Defence Review. The task team made it clear that the decrease in funding levels was highly problematic, and that inadequate funding would eventually severely compromise the defence capabilities of the SANDF. They emphasised that the government had to decide on one of two options: approving a greater budget allocation to the SANDF or alternatively opting for a significantly scaled-down level of ambition and commitment which is aligned to the budget allocation. One thing was clear: South Africa’s spending was low in terms of comparative international military spending practice. Since 2015 defence spending in South Africa has declined even further to about 0.7% of GDP, which is way below the international norm of more or less 2% of GDP.

Despite its budgetary challenges, in 2023, the SANDF was the fifth largest troop-contributing nation in the UN’s operation in the eastern DRC and played a key role in the SADC operation against insurgents in northern Mozambique from 2021 to 2024. However, considering the history of SANDF operations, a major problem is that the SANDF’s deployments tend to be open-ended, resulting in protracted deployments with serious implications for the defence budget. Moreover, there is no plan to either opt for an adequate defence budget on the one hand, or to scale down the level of political ambition on the other.

It should also be noted that border protection and support for the South African Police Service (SAPS) in internal operations have become increasingly important and demanding in the SANDF’s activities and responsibilities and can even be regarded as among its primary functions. However, a major concern is that the SANDF is too often used as a stopgap in South Africa’s domestic security landscape — hindering its ability to function as a professional, well-equipped armed force with a clear mandate.

For instance, in 2023, politicians called on the SANDF to assist in combating violence linked to zama zamas after the government deployed soldiers in large numbers to curb illegal mining activities. Even local communities expect the government to utilise the SANDF internally, adding pressure on the state to consider such deployments. In this context, the SANDF has little choice but to respond to political calls to assist the SAPS in maintaining internal security. Another recent example of internal deployment was the government’s decision in 2023 to deploy the SANDF to safeguard the coal power plants of South Africa’s major power utility, Eskom.

In conclusion, it should be clear from the above that there is a significant mismatch between what is expected of the SANDF at the political level and its budget and capabilities. The challenge for the SANDF is that defence remains central to its raison d’être, yet it must also be ready to respond to political calls for assistance in peace and security operations across the continent. Additionally, the SANDF is expected to support the SAPS in providing security services in a crime-ridden and fragile South African society — all while operating on a budget of approximately 0.7% of the country’s GDP. It is therefore no surprise that the SANDF is often described as institutionally overstretched and has, in fact, been in a state of ongoing decline for some time.

Critics can rightly argue that the South African government has shown little to no political will to address the SANDF’s financial challenges over the past two decades, contributing to the difficulties its members face in defending themselves against the M23 rebels in the DRC. At the same time, growing fiscal pressures and severe socio-economic challenges leave the government in a weak position to significantly increase the defence budget. Be that as it may, the SANDF’s troubles in the DRC mark a low point for the institution. Perhaps now is the time to reassess both its mandate and funding, particularly in light of the persistent gap between political expectations and available resources.

News Archive

Power interruptions: Information for internal communication
2008-01-31

As part of the UFS’s commitment to address load shedding, the management would like to communicate the following:

The UFS mainly deals with the power interruptions by way of (a) the possible installation of equipment (e.g. generators) and (b) operational arrangements to ensure the functioning of the UFS in spite of power interruptions.

During the past week progress was made on both fronts. The information that follows resulted from a meeting of a task team of Physical Resources led by Mr Nico Janse van Rensburg, which took place on Monday 28 January (this task team naturally focuses on physical solutions) and a discussion by Exco on Wednesday 30 January 2008. Exco discussed the recommendations of the mentioned task team in respect of physical aspects, as well as the operational arrangements proposed by faculties.

Physical solutions

A Main Campus

1. New emergency power installations already approved:

Last week Exco gave its approval for the design and installation of emergency power equipment in all the large lecture-hall complexes to proceed immediately.

In all these cases

  • load surveys have been completed and a start has been made with the ordering of equipment and the process of appointing contractors. (Exco approved the adjustment of normal tender procedures in an attempt to expedite completion.)
  • generators with 20-30% more capacity than required for the current load are being ordered.
  • provision is being made for the connection of lights and at least one wall plug to the emergency power.
  • the expected construction time is 16 weeks (except in the case of the Flippie Groenewoud Building where it is 6 weeks).

The above-mentioned concerns lecture halls/ venues in the following buildings: Examination Centre, Flippie Groenewoud Building, Stabilis, Genmin and the Agriculture Building.

As far as the Agriculture Building is concerned, a larger generator (larger than required for lecture venues only) is being ordered in view of simultaneously providing essential research equipment (refrigerators, ovens, glasshouses) with emergency power within 16 weeks.

2. Investigation into the optimal utilisation of present emergency power installations

All the emergency power systems are being investigated on the basis of a list compiled in 2006 to determine whether excess capacity is available and whether it is possible to connect additional essential equipment or lights to it.

The electrical engineer warns as follows:
“Staff members must under no circumstances overload present emergency power points.

A typical example of this is a laboratory with 10 power points of which 2 points are emergency power outlets. Normally a fridge and freezer would, for example, be plugged into the two emergency power points, but now, with long load-shedding interruptions, a considerably larger number of appliances are being plugged into the power point by means of multi-sockets and extension cords. In the end the effect of such connections will accumulate at the emergency generator, which will then create a greater danger of it being overloaded and tripping, in other words, no emergency power will then be available.”

3. Requests and needs addressed directly to Physical Resources or reported to Exco via the line managers.

All the physical needs and requests addressed directly to Physical Resources or submitted to Exco via the line managers are being listed, classified and considered technically in view of their being discussed by the task team on Monday 11 February.
The information will (a) lead to recommendations to Exco regarding possible additional urgent emergency power installations, and (b) be used in the comprehensive investigation into the UFS’s preparedness for and management of long power interruptions.

Requests that can easily be complied with immediately and that fit into the general strategy will indeed be dealt with as soon as possible.

4. Purchase of loose-standing equipment: light, small, loose-standing generators, UPSs as solutions to/ aids during power interruptions

Exco approved that

a) faculties and support services accept responsibility themselves for the funding and purchase of loose equipment such as, for example battery lights, should they regard these as essential.
b) UPSs (uninterruptible power supplies) that faculties and support services wish to purchase to combat the detrimental effect of unexpected power interruptions on computer equipment) can (as at present) be purchased from own funds via Computer Services.
c) UPSs (uninterruptible power supplies) that faculties and support services wish to purchase to combat the detrimental effect of unexpected power interruptions on other types of equipment can normally be purchased from own funds with the consent of the line manager concerned.
Note: Please just make sure of the appropriateness of the equipment for a specific situation: it is not a power supply that can bridge a two-hour power interruption.)
d) small, loose-standing generators can be purchased from own funds via Physical Resources and installed under their supervision.
e) laptop computers can , where necessary, be purchased from own budgets. The availability of second-hand laptop computers must be taken into account.

B Vista

No major problems have been reported to date. The situation is being monitored and will be managed according to need. The same guidelines that apply to the Main Campus will naturally also apply to the Vista Campus.

C Qwaqwa

The situation is receiving attentions and solutions have already been found for most problems.

D General

1. All-inclusive project
A comprehensive investigation into the UFS’s preparedness for and management of long power interruptions will be launched as soon as possible. Available capacity will be utilised first to alleviate the immediate need. The needs assessment to which all faculties and support services have already contributed is already an important building block of the larger project.

2. Building and construction projects currently in the planning and implementation phase
The need for emergency power for projects such as the new Computer Laboratory is being investigated proactively and will be addressed in a suitable manner.

3. Liaison with Centlec
Attempts at direct and continuous liaison are continuing in an attempt to accommodate the unique needs of the UFS.

4. HESA meeting and liaison with other universities
A representative of the UFS will attend a meeting of all higher education institutions on 11 February. The meeting is being arranged by HESA (Higher Education South Africa) to discuss the implications for the sector, the management of risks and the sector’s response to government.

5. Internal communication
It is the intention to communicate internally after every meeting of the task team, which will take place on Mondays. Strategic Communication will assist in this regard.


 

We use cookies to make interactions with our websites and services easy and meaningful. To better understand how they are used, read more about the UFS cookie policy. By continuing to use this site you are giving us your consent to do this.

Accept