18 June 2019 | Story Leonie Bolleurs | Photo Leonie Bolleurs
Dr Christine Engelbrecht from the Agricultural Research Council
Dr Christine Engelbrecht from the Agricultural Research Council presented the keynote lecture on climate dynamics, predicting that El Niños will double in frequency towards the end of the century.

The world will need nearly double the current food supply by 2050 to feed an ever-increasing world population. This is a mammoth, almost impossible task.

Building on knowledge

According to UFS Rector and Vice-Chancellor, Prof Francis Petersen, if we approach challenges such as these with scientific level-headedness, systematically build on knowledge and experience gained, and draw on similar inputs from other specialist fields, the seemingly impossible becomes possible.

“To what extent do we integrate our knowledge across sectors – within the university and outside the university; on the continent as well as globally?” he asked the 300-plus delegates, which included animal scientists, students, and various other role players in the livestock sector, at the 51st South African Society of Animal Science (SASAS) congress on the Bloemfontein Campus of the University of the Free State (UFS). 

Willingness to adapt to new strategies


The theme of this year’s congress was: Managing the ecological footprint of livestock through efficient production. The congress provided a platform for discussions on the impact of livestock production – bringing in elements of critical thinking, as well as the willingness to adopt new strategies. 

During the congress, workshops on topics such as silage, predation management, intensive sheep production, prickly-pear utilisation, and animal welfare provided delegates with the opportunity to discuss challenges faced by the South African livestock producer.

Dr Christine Engelbrecht (Meteorology) from the Agricultural Research Council presented the first keynote address, focusing on climate dynamics. 

“We have high-impact weather systems across Southern Africa. It is projected that strong El Niños are to double in frequency towards the end of the 21st century,” said Dr Engelbrecht. 

She further predicted temperature increases of between 4 and 7 degrees Celsius in the interior before the end of the century. Over the Free State, Northern Cape, and North-West Province, we can expect shorter frost seasons, significant increases in maximum temperatures for both summer and winter, as well as more frequent El Niño-induced droughts. 

Ecological footprint of food

Improved production outputs need to be achieved by using less land, water, and available energy, while ensuring that the degradation and pollution of natural resources are limited. A scientific approach would be a viable option to improve the efficiency of livestock production.

SASAS President, Prof Este van Marle-Köster from the University of Pretoria, pointed out that all food had an ecological impact.

Dr Frikkie Maré, Head of the Department of Agricultural Economics at the UFS, presented a keynote lecture on managing the footprint of beef through efficient production. Comparing the water footprint of different cattle breeds, his question was what could be done to reduce this. 

Animal welfare was introduced to the congress for the first time. Prof Cathy Dwyer from Scotland’s Rural College presented a session on, ‘Can animal welfare contribute to improved production efficiency?’

The oldest conception of animal welfare is the five freedoms adapted to the five welfare needs of animals, namely a suitable environment, a suitable diet, exhibiting normal behaviour patterns, being with or being apart from other animals, and protection from pain, injury, suffering, and disease. Studies demonstrate that animal welfare can be an important and effective part of production efficiency, and that animal welfare should be seen as an integral component of improving the sustainability of livestock. 

Prof HO de Waal from the Predation Management Centre at the UFS presented a session on the impact of predation on livestock production, with the tile: The need for coordinated predation management in South Africa – quo vadis? He said: “The current approach to predation management is fragmented and uncoordinated. Solutions for the management of human-wildlife conflict require a South African institutional memory. Most of the information on predation and the hunting of predators is held by specialist predator hunters and farmers. In a system of coordinated predation management, farmers and government are equal partners, each with specific responsibilities.”

News Archive

Power interruptions: Information for internal communication
2008-01-31

As part of the UFS’s commitment to address load shedding, the management would like to communicate the following:

The UFS mainly deals with the power interruptions by way of (a) the possible installation of equipment (e.g. generators) and (b) operational arrangements to ensure the functioning of the UFS in spite of power interruptions.

During the past week progress was made on both fronts. The information that follows resulted from a meeting of a task team of Physical Resources led by Mr Nico Janse van Rensburg, which took place on Monday 28 January (this task team naturally focuses on physical solutions) and a discussion by Exco on Wednesday 30 January 2008. Exco discussed the recommendations of the mentioned task team in respect of physical aspects, as well as the operational arrangements proposed by faculties.

Physical solutions

A Main Campus

1. New emergency power installations already approved:

Last week Exco gave its approval for the design and installation of emergency power equipment in all the large lecture-hall complexes to proceed immediately.

In all these cases

  • load surveys have been completed and a start has been made with the ordering of equipment and the process of appointing contractors. (Exco approved the adjustment of normal tender procedures in an attempt to expedite completion.)
  • generators with 20-30% more capacity than required for the current load are being ordered.
  • provision is being made for the connection of lights and at least one wall plug to the emergency power.
  • the expected construction time is 16 weeks (except in the case of the Flippie Groenewoud Building where it is 6 weeks).

The above-mentioned concerns lecture halls/ venues in the following buildings: Examination Centre, Flippie Groenewoud Building, Stabilis, Genmin and the Agriculture Building.

As far as the Agriculture Building is concerned, a larger generator (larger than required for lecture venues only) is being ordered in view of simultaneously providing essential research equipment (refrigerators, ovens, glasshouses) with emergency power within 16 weeks.

2. Investigation into the optimal utilisation of present emergency power installations

All the emergency power systems are being investigated on the basis of a list compiled in 2006 to determine whether excess capacity is available and whether it is possible to connect additional essential equipment or lights to it.

The electrical engineer warns as follows:
“Staff members must under no circumstances overload present emergency power points.

A typical example of this is a laboratory with 10 power points of which 2 points are emergency power outlets. Normally a fridge and freezer would, for example, be plugged into the two emergency power points, but now, with long load-shedding interruptions, a considerably larger number of appliances are being plugged into the power point by means of multi-sockets and extension cords. In the end the effect of such connections will accumulate at the emergency generator, which will then create a greater danger of it being overloaded and tripping, in other words, no emergency power will then be available.”

3. Requests and needs addressed directly to Physical Resources or reported to Exco via the line managers.

All the physical needs and requests addressed directly to Physical Resources or submitted to Exco via the line managers are being listed, classified and considered technically in view of their being discussed by the task team on Monday 11 February.
The information will (a) lead to recommendations to Exco regarding possible additional urgent emergency power installations, and (b) be used in the comprehensive investigation into the UFS’s preparedness for and management of long power interruptions.

Requests that can easily be complied with immediately and that fit into the general strategy will indeed be dealt with as soon as possible.

4. Purchase of loose-standing equipment: light, small, loose-standing generators, UPSs as solutions to/ aids during power interruptions

Exco approved that

a) faculties and support services accept responsibility themselves for the funding and purchase of loose equipment such as, for example battery lights, should they regard these as essential.
b) UPSs (uninterruptible power supplies) that faculties and support services wish to purchase to combat the detrimental effect of unexpected power interruptions on computer equipment) can (as at present) be purchased from own funds via Computer Services.
c) UPSs (uninterruptible power supplies) that faculties and support services wish to purchase to combat the detrimental effect of unexpected power interruptions on other types of equipment can normally be purchased from own funds with the consent of the line manager concerned.
Note: Please just make sure of the appropriateness of the equipment for a specific situation: it is not a power supply that can bridge a two-hour power interruption.)
d) small, loose-standing generators can be purchased from own funds via Physical Resources and installed under their supervision.
e) laptop computers can , where necessary, be purchased from own budgets. The availability of second-hand laptop computers must be taken into account.

B Vista

No major problems have been reported to date. The situation is being monitored and will be managed according to need. The same guidelines that apply to the Main Campus will naturally also apply to the Vista Campus.

C Qwaqwa

The situation is receiving attentions and solutions have already been found for most problems.

D General

1. All-inclusive project
A comprehensive investigation into the UFS’s preparedness for and management of long power interruptions will be launched as soon as possible. Available capacity will be utilised first to alleviate the immediate need. The needs assessment to which all faculties and support services have already contributed is already an important building block of the larger project.

2. Building and construction projects currently in the planning and implementation phase
The need for emergency power for projects such as the new Computer Laboratory is being investigated proactively and will be addressed in a suitable manner.

3. Liaison with Centlec
Attempts at direct and continuous liaison are continuing in an attempt to accommodate the unique needs of the UFS.

4. HESA meeting and liaison with other universities
A representative of the UFS will attend a meeting of all higher education institutions on 11 February. The meeting is being arranged by HESA (Higher Education South Africa) to discuss the implications for the sector, the management of risks and the sector’s response to government.

5. Internal communication
It is the intention to communicate internally after every meeting of the task team, which will take place on Mondays. Strategic Communication will assist in this regard.


 