23 June 2022 | Story Dr Olivia Kunguma | Photo Supplie
Dr Olivia Kunguma
Dr Olivia Kunguma is a lecturer in the Disaster Management Training and Education Centre for Africa (DiMTEC) at UFS.

Opinion article by Dr Olivia Kunguma, Disaster Management Training and Education Centre for Africa, University of the Free State.
On 13 April 2022, the National Disaster Management Centre (NDMC) 'classified' the KwaZulu-Natal (KZN) floods as a provincial disaster in terms of Section 23 of the Disaster Management Act, 57 of 2002 (DMA). Following the classification, the KZN provincial government 'declared' a provincial state of disaster in terms of Section 41 of the DMA. Subsequent to this declaration and after considering reports from other provinces such as Eastern Cape and North West that were also affected by floods, on 18 April 2022, the disaster was reclassified. Following a consultation with the Cabinet, the Minister of Cooperative Governance and Traditional Affairs, Dr Nkosazana Dlamini-Zuma declared a national state of disaster. The national state of disaster was in terms of Section 27(1) and Section 23(6)(a)(b), which states that a disaster is a national disaster if it affects more than one province or if a single province is unable to deal with the disaster effectively. Another primary purpose of a national declaration was because the existing legislation and contingency arrangements of the affected state organs were insufficient to handle the provincial disaster and a need to activate other extraordinary measures as and when required. Also, the provincial disaster declaration was insufficient, given the widespread magnitude of the KZN floods. Since Durban has a port on which the entire nation and the Southern African region depend, the disaster had implications beyond the province. The Department of Cooperative Governance (DCOG) is the leading government department coordinating all stakeholders and intervention measures to address the effects of the disaster. The department is following a three-phased approach to support the affected provinces. The approach includes; immediate humanitarian relief, stabilisation and recovery, and rehabilitation and reconstruction.

Before the flooding disaster the KZN community was already vulnerable to xenophobic attacks, the COVID-19 pandemic, and civil unrest. The flooding disaster exacerbated the communities’ vulnerability and had a severe social, economic and environmental impact. At least 461 people lost their lives, about 874 companies were affected, 40 000 people were displaced, more than 40 people were reported missing, and damage to infrastructure was estimated at more than R20 billion. Mindful of all these challenges, local and international organisations and local communities extended a helping hand to those affected by the disaster. 

South Africa’s general response to disasters

As stated earlier, South Africa has been exposed to various hazards, some declared disasters by the government. In the past decade alone, xenophobic attacks on foreign nationals were declared a disaster in 2015; in 2018-2020 a drought was declared a disaster. In 2021, riots and looting in KZN were declared a disaster. Now the 2022 flooding has been declared a disaster. The occurrence and effect of hazards and the capabilities of the people affected to respond determines the need for a disaster declaration. Once a disaster has been declared, the necessary resources will be released. The point in question here is, “Is South Africa’s response to disasters adequate, timely and enough to assist affected communities?” The answer is the response is 'fair'. The fact that there is good disaster legislation that guides the process makes it a positive starting point. The challenge where timeliness is affected is the lengthy process of declaring the disaster so that the response can take place quickly. The response to xenophobic attacks was slow and inadequate because the government did not know how to classify the hazard. The response to the KZN looting and recent KZN flooding was also slow and inadequate, leading to significant impacts. To improve the response to disasters the proactive involvement of all stakeholders is needed, where all organs of state have sufficient resources and are prepared to respond to hazards in their custodianship, for example, drought, is the responsibility of the Department of Agriculture. 

Procedures for handling donations and relief

Organisations and individuals come together to respond to and assist victims of the disaster. With all volunteers coming together, the duplication of efforts is anticipated. According to the South African National Disaster Management Framework (NDMF) of 2005, the Disaster Management Centres must establish appropriate protocols to clarify procedures for requesting assistance and discourage ad hoc and unsolicited appeals for relief. Any possibilities of duplication are mitigated by establishing a Joint Operating Committee (JOC). Activating a JOC helps standardise reporting protocols and improve the coordination of interventions. Specific organisations form part of the JOC with allocated roles and responsibilities based on the disaster. For example, the Department of Social Development is responsible for conducting needs assessments and distributing relief items.

Furthermore, each stakeholder forming part of the JOC should implement the existing contingency or response plans and establish standard operating protocols or procedures (SOPs) for coordinating response and recovery operations as per their mandate. Some organisations do have SOPs, response or contingency plans, but due to the magnitude of the disaster, they could not be used effectively. The NDMF mandates the development of Regulations for the Practice and Management of Relief Operations. The regulations must be gazetted and must include relief standards and the duration of relief efforts. A JOC was established at metropolitan and provincial levels regarding the KZN flood disaster. Each JOC has a Disaster Management Relief Team (DMRT). This team is responsible for receiving donations and distributing them. The donating individuals or organisations contact the DMRT to handle the donations. The DMRT also allows the donors to select where they want their donations to go. Organisations that wish to contribute financially are urged to contribute to a Disaster Relief Fund account.

The Disaster Management Training and Education Centre for Africa (DiMTEC) joined in the initiative and called on the University of the Free State (UFS) and Bloemfontein community to donate non-perishable food and non-food items to the KZN flood disaster victims. 

DiMTEC staff
Staff members from the Disaster Management Training and Education Centre for Africa (DiMTEC) at UFS
in Durban. (Photo: Supplied)

After several weeks of collecting donations, the UFS-DiMTEC personnel travelled to Durban on 29 May to deliver the goods and visited some areas affected by the floods. The eThekwini Disaster Management and Emergency Control Unit staff thanked the UFS-DiMTEC personnel and the Bloemfontein community for the donations they made. “We appreciate your effort to deliver the donations to the flood victims personally. We would also like to invite UFS-DiMTEC to form collaborations with us as we have done with the Durban University of Technology. The collaborations will help us with disaster risk reduction efforts and build resilient communities,” said Mr Vincent Ngubane, the Head of eThekwini Disaster Management and Emergency Control Unit. Following the meeting with the Head of the Centre, the UFS-DiMTEC team was escorted to three shelters (KwaNdengezi Hall, Mariannridge Hall and Eshcol Community Church), most of which housed children from as young as six years of age. The challenges faced by the shelters include possibilities of theft, limited water and sanitation access, power cuts and inadequate food. 

Conjecture of KZN flooding disaster

Several media articles have recorded possible causes of the flooding and landslides disaster in KZN, and here are some of them:
• Slope instabilities relating to the local geology and topography influenced by climate change
• Hilly areas with significant gorges and ravines that are conducive to floods
• Common ‘cut-off low’ which brings heavy rain, damaging winds and cold weather mostly in autumn and spring
• Unmaintained storm-water drainage systems
• Housing shortages due to migration and lack of affordability that lead to informal settlements
• Apartheid legacy placed the poor in the periphery along low-lying areas and floodplains
• Social production (natural hazards interacting with a vulnerable population)
• Lack of science awareness among politicians, and toxic politics
• Poor planning and governance

Building back KZN better

While the KZN disaster response is ongoing, recovery and rehabilitation talks are in place. The DMA (Section 1) defines recovery and rehabilitation as a post-disaster phase that includes efforts and developments to normalise or restore a condition caused by a disaster. The effects of the disaster are mitigated, and circumstances that will mitigate or prevent a similar disaster are created. Before this phase commences, the government and other responsible stakeholders must effectively and scientifically conduct impact and risk assessments to inform resilient reconstruction. Climate change (heavy rains), environmental change (soil), and human and societal dynamics (settlements/civil unrest) are some of the factors that should be at the core of the KZN recovery and rehabilitation planning. Building back better in KZN requires the identification of better land for rebuilding. Overly, the earlier stated possible root causes of the flood disaster need to be scientifically researched to consider the findings in the recovery and rehabilitation phase. Funding is required for all this to happen, and the funds must be properly managed. While political support is a requirement, administrative structures must not be throttled. 

Donated items for flood stricken KZN
Some of the items donated to flood stricken Durban by UFS DiMTEC (Photo: Supplied)


Relief still needed during recovery and rehabilitation 

Although the KZN province is slowly transitioning from response and relief to recovery and rehabilitation, the disaster is far from over. While relief will still be needed to assist those in need, it must be reduced to avoid dependency. Currently, the disaster managers are dealing with challenges such as community members not affected coming to settle in community halls to benefit from free meals. Some community hall members have started complaining about the food and requesting specific meals. Nonetheless, the NDMF states that the prolonged relief supply creates dependency and discourages risk ownership, which is imperative for building resiliency.

Moreover, continued provision of relief reinforces risk transfer to external support, government or humanitarian agencies. The government needs to speed up the transition from relief to resilient rehabilitation without making further development mistakes. During this process, the KZN community must participate in the building back better process at all phases. 

Meanwhile, the UFS-DiMTEC is still appealing to the UFS community and the City of Bloemfontein to continue donating. Those wishing to donate are urged to drop off the items at the following drop-off point: Agriculture Building/Landbou, DiMTEC, First Floor, Room 3.102A, Bloemfontein. For more information regarding donations, please get in touch with Dr Tlou Raphela at +27 72 108 4987 or Raphelatd@ufs.ac.za

News Archive

Power interruptions: Information for internal communication
2008-01-31

As part of the UFS’s commitment to address load shedding, the management would like to communicate the following:

The UFS mainly deals with the power interruptions by way of (a) the possible installation of equipment (e.g. generators) and (b) operational arrangements to ensure the functioning of the UFS in spite of power interruptions.

During the past week progress was made on both fronts. The information that follows resulted from a meeting of a task team of Physical Resources led by Mr Nico Janse van Rensburg, which took place on Monday 28 January (this task team naturally focuses on physical solutions) and a discussion by Exco on Wednesday 30 January 2008. Exco discussed the recommendations of the mentioned task team in respect of physical aspects, as well as the operational arrangements proposed by faculties.

Physical solutions

A Main Campus

1. New emergency power installations already approved:

Last week Exco gave its approval for the design and installation of emergency power equipment in all the large lecture-hall complexes to proceed immediately.

In all these cases

  • load surveys have been completed and a start has been made with the ordering of equipment and the process of appointing contractors. (Exco approved the adjustment of normal tender procedures in an attempt to expedite completion.)
  • generators with 20-30% more capacity than required for the current load are being ordered.
  • provision is being made for the connection of lights and at least one wall plug to the emergency power.
  • the expected construction time is 16 weeks (except in the case of the Flippie Groenewoud Building where it is 6 weeks).

The above-mentioned concerns lecture halls/ venues in the following buildings: Examination Centre, Flippie Groenewoud Building, Stabilis, Genmin and the Agriculture Building.

As far as the Agriculture Building is concerned, a larger generator (larger than required for lecture venues only) is being ordered in view of simultaneously providing essential research equipment (refrigerators, ovens, glasshouses) with emergency power within 16 weeks.

2. Investigation into the optimal utilisation of present emergency power installations

All the emergency power systems are being investigated on the basis of a list compiled in 2006 to determine whether excess capacity is available and whether it is possible to connect additional essential equipment or lights to it.

The electrical engineer warns as follows:
“Staff members must under no circumstances overload present emergency power points.

A typical example of this is a laboratory with 10 power points of which 2 points are emergency power outlets. Normally a fridge and freezer would, for example, be plugged into the two emergency power points, but now, with long load-shedding interruptions, a considerably larger number of appliances are being plugged into the power point by means of multi-sockets and extension cords. In the end the effect of such connections will accumulate at the emergency generator, which will then create a greater danger of it being overloaded and tripping, in other words, no emergency power will then be available.”

3. Requests and needs addressed directly to Physical Resources or reported to Exco via the line managers.

All the physical needs and requests addressed directly to Physical Resources or submitted to Exco via the line managers are being listed, classified and considered technically in view of their being discussed by the task team on Monday 11 February.
The information will (a) lead to recommendations to Exco regarding possible additional urgent emergency power installations, and (b) be used in the comprehensive investigation into the UFS’s preparedness for and management of long power interruptions.

Requests that can easily be complied with immediately and that fit into the general strategy will indeed be dealt with as soon as possible.

4. Purchase of loose-standing equipment: light, small, loose-standing generators, UPSs as solutions to/ aids during power interruptions

Exco approved that

a) faculties and support services accept responsibility themselves for the funding and purchase of loose equipment such as, for example battery lights, should they regard these as essential.
b) UPSs (uninterruptible power supplies) that faculties and support services wish to purchase to combat the detrimental effect of unexpected power interruptions on computer equipment) can (as at present) be purchased from own funds via Computer Services.
c) UPSs (uninterruptible power supplies) that faculties and support services wish to purchase to combat the detrimental effect of unexpected power interruptions on other types of equipment can normally be purchased from own funds with the consent of the line manager concerned.
Note: Please just make sure of the appropriateness of the equipment for a specific situation: it is not a power supply that can bridge a two-hour power interruption.)
d) small, loose-standing generators can be purchased from own funds via Physical Resources and installed under their supervision.
e) laptop computers can , where necessary, be purchased from own budgets. The availability of second-hand laptop computers must be taken into account.

B Vista

No major problems have been reported to date. The situation is being monitored and will be managed according to need. The same guidelines that apply to the Main Campus will naturally also apply to the Vista Campus.

C Qwaqwa

The situation is receiving attentions and solutions have already been found for most problems.

D General

1. All-inclusive project
A comprehensive investigation into the UFS’s preparedness for and management of long power interruptions will be launched as soon as possible. Available capacity will be utilised first to alleviate the immediate need. The needs assessment to which all faculties and support services have already contributed is already an important building block of the larger project.

2. Building and construction projects currently in the planning and implementation phase
The need for emergency power for projects such as the new Computer Laboratory is being investigated proactively and will be addressed in a suitable manner.

3. Liaison with Centlec
Attempts at direct and continuous liaison are continuing in an attempt to accommodate the unique needs of the UFS.

4. HESA meeting and liaison with other universities
A representative of the UFS will attend a meeting of all higher education institutions on 11 February. The meeting is being arranged by HESA (Higher Education South Africa) to discuss the implications for the sector, the management of risks and the sector’s response to government.

5. Internal communication
It is the intention to communicate internally after every meeting of the task team, which will take place on Mondays. Strategic Communication will assist in this regard.


 