 President Cyril Ramaphosa delivered the State of the Nation Address (SONA) as the first president without an ANC majority in Parliament. He addressed several critical issues, committing his Government of National Unity (GNU) departments to take decisive action to tackle the persistent challenges of unemployment, poverty, and inequality. The strategy involves prioritising inclusive growth, job creation, poverty alleviation, and building a capable, ethical, and developmental state. Additionally, the president emphasised the need for national dialogue and pledged to reform local governance through a review of the 1998 White Paper on Local Government.

The current White Paper defines developmental local government as a system committed to working with citizens and community groups to find sustainable ways to meet social, economic, and material needs while enhancing the quality of life. It emphasises targeting marginalised and excluded groups within communities, such as women, people with disabilities, and those living in extreme poverty. Highlighting the central role of local government, South African Local Government Association (Salga) president Bheki Stofile noted that local governments are responsible for delivering 46% of public services, including water supply, electricity, sanitation, and refuse removal, yet receive only 10% of national revenue. At the same time, municipalities have accumulated a staggering total debt of R386.5 billion and owe creditors R117.5 billion.

To say that local government is in crisis would be an understatement. The 30-year government review reveals that economic, political, spatial, and institutional disparities hinder municipalities’ ability to deliver services. An estimated 29% of municipalities are on the verge of operational collapse, pointing to systemic dysfunction rooted in governance failures and limited capacity. Research conducted by the Centre for Gender and Africa Studies at the University of the Free State in partnership with the Local Government Seta over the past three years confirms the poor state of knowledge management, the lack of evidence-based human resource development practices, persistent barriers facing women in local government, and challenges in implementing the Municipal Staff Regulations. Simply increasing fiscal allocations to local government without addressing the root causes of these failures would be like pouring money down the drain.

The case for local dialogues

Any conversation about building a capable state must begin with functional, ethical, and developmental local governance. This requires shifting from a national dialogue to local dialogues that can feed into a national dialogue. For the past 25 years, local governments have produced five-year Integrated Development Plans (IDPs) in partnership with communities, yet the outcomes have been disappointing. We have failed to transform data into actionable knowledge that can tackle challenges in a participatory manner. The marginalised and poor have become passive spectators in a system meant to empower them. They lack agency and have lost confidence in local government and the ward committee system, which was designed to be the functional backbone of participatory democracy. Meanwhile, the middle class, equipped with agency and resources, has become increasingly disengaged. What we are witnessing is a form of “wicked compliance” — a tick-box approach to democracy that echoes the late Malcolm X’s critique: “We do not have a democracy... we have hypocrisy.”

To move beyond this, the local government review must be accompanied by local dialogues, led by community members, businesses, academia, and local government, as envisioned in the National Development Plan (NDP). However, these dialogues should not be led by local government but rather by the collective. This represents a shift from traditional government (top-down) to governance (co-created), as advocated by sociologist Francois Theron. Such co-created spaces allow communities to craft pragmatic future visions and strategise from the future backward. These dialogues should encourage genuine and innovative conversations about the future, positioning local government as a co-creator and collaborator, rather than simply another participant in a talk shop.

Framework for future-focused local dialogues

A future-focused local dialogue should be addressed using the Governance 5iQ framework that asks five fundamental governance questions:

1. Why do we do what we do? (Vision)
2. How do we do what we do? (Mission)
3. How do we know we are on track? (Monitoring and Evaluation)
4. What do we do if we are not on track? (Consequence Management)

5. How do we lead and learn? (Knowledge Management)

For local governance to be effective, policies must be implemented by committed, competent, and caring individuals. Additionally, policies should be reviewed to assess whether they create opportunities for the poor and the youth. If local economic development is to succeed, then supply chain processes must be aligned with developmental objectives. A valuable case study is Daleel Jacobs, Supply Chain Manager at Stellenbosch Municipality, whose master’s thesis demonstrates innovative ways to fulfil the spirit of the law while delivering tangible outcomes.

Addressing political interference and embracing digital transformation

Research conducted across 32 municipalities in all nine provinces reveals that political interference is a significant barrier to effective implementation. Politicians are frequently accused of meddling, overstepping their boundaries, and lacking both insight and foresight. As coalitions become more common post-2026 elections, political parties must adopt transparent candidate-vetting processes. The Coalition Bill could provide much-needed stability by introducing an executive committee system where power is proportionally distributed in the absence of a majority party. Moreover, local governments must leverage digital transformation. In August 2024, the government launched the National Artificial Intelligence Policy Framework. Local governments should harness AI tools to enhance efficiency and effectiveness. Following the example of the University of Kehl in Germany, which introduced a degree in Digital Public Management five years ago, South African institutions should also prepare the next generation of public managers for a digital future.

Leading into the future

South Africa's vibrant democracy is mirrored by the volatility, uncertainty, complexity, and ambiguity that characterise local governance. Leaders are tasked with bringing clarity and certainty, eliminating contradictions, and fostering a compelling vision of the future. However, crafting a vision is not enough; we must actively work towards and embody this preferred future.

The president may deliver the SONA, but the true state of the nation depends on all of us. By prioritising local dialogues and a collaborative governance model, we can lay the foundation for sustainable local governance that truly serves the people.

News Archive

Power interruptions: Information for internal communication
2008-01-31

As part of the UFS’s commitment to address load shedding, the management would like to communicate the following:

The UFS mainly deals with the power interruptions by way of (a) the possible installation of equipment (e.g. generators) and (b) operational arrangements to ensure the functioning of the UFS in spite of power interruptions.

During the past week progress was made on both fronts. The information that follows resulted from a meeting of a task team of Physical Resources led by Mr Nico Janse van Rensburg, which took place on Monday 28 January (this task team naturally focuses on physical solutions) and a discussion by Exco on Wednesday 30 January 2008. Exco discussed the recommendations of the mentioned task team in respect of physical aspects, as well as the operational arrangements proposed by faculties.

Physical solutions

A Main Campus

1. New emergency power installations already approved:

Last week Exco gave its approval for the design and installation of emergency power equipment in all the large lecture-hall complexes to proceed immediately.

In all these cases

  • load surveys have been completed and a start has been made with the ordering of equipment and the process of appointing contractors. (Exco approved the adjustment of normal tender procedures in an attempt to expedite completion.)
  • generators with 20-30% more capacity than required for the current load are being ordered.
  • provision is being made for the connection of lights and at least one wall plug to the emergency power.
  • the expected construction time is 16 weeks (except in the case of the Flippie Groenewoud Building where it is 6 weeks).

The above-mentioned concerns lecture halls/ venues in the following buildings: Examination Centre, Flippie Groenewoud Building, Stabilis, Genmin and the Agriculture Building.

As far as the Agriculture Building is concerned, a larger generator (larger than required for lecture venues only) is being ordered in view of simultaneously providing essential research equipment (refrigerators, ovens, glasshouses) with emergency power within 16 weeks.

2. Investigation into the optimal utilisation of present emergency power installations

All the emergency power systems are being investigated on the basis of a list compiled in 2006 to determine whether excess capacity is available and whether it is possible to connect additional essential equipment or lights to it.

The electrical engineer warns as follows:
“Staff members must under no circumstances overload present emergency power points.

A typical example of this is a laboratory with 10 power points of which 2 points are emergency power outlets. Normally a fridge and freezer would, for example, be plugged into the two emergency power points, but now, with long load-shedding interruptions, a considerably larger number of appliances are being plugged into the power point by means of multi-sockets and extension cords. In the end the effect of such connections will accumulate at the emergency generator, which will then create a greater danger of it being overloaded and tripping, in other words, no emergency power will then be available.”

3. Requests and needs addressed directly to Physical Resources or reported to Exco via the line managers.

All the physical needs and requests addressed directly to Physical Resources or submitted to Exco via the line managers are being listed, classified and considered technically in view of their being discussed by the task team on Monday 11 February.
The information will (a) lead to recommendations to Exco regarding possible additional urgent emergency power installations, and (b) be used in the comprehensive investigation into the UFS’s preparedness for and management of long power interruptions.

Requests that can easily be complied with immediately and that fit into the general strategy will indeed be dealt with as soon as possible.

4. Purchase of loose-standing equipment: light, small, loose-standing generators, UPSs as solutions to/ aids during power interruptions

Exco approved that

a) faculties and support services accept responsibility themselves for the funding and purchase of loose equipment such as, for example battery lights, should they regard these as essential.
b) UPSs (uninterruptible power supplies) that faculties and support services wish to purchase to combat the detrimental effect of unexpected power interruptions on computer equipment) can (as at present) be purchased from own funds via Computer Services.
c) UPSs (uninterruptible power supplies) that faculties and support services wish to purchase to combat the detrimental effect of unexpected power interruptions on other types of equipment can normally be purchased from own funds with the consent of the line manager concerned.
Note: Please just make sure of the appropriateness of the equipment for a specific situation: it is not a power supply that can bridge a two-hour power interruption.)
d) small, loose-standing generators can be purchased from own funds via Physical Resources and installed under their supervision.
e) laptop computers can , where necessary, be purchased from own budgets. The availability of second-hand laptop computers must be taken into account.

B Vista

No major problems have been reported to date. The situation is being monitored and will be managed according to need. The same guidelines that apply to the Main Campus will naturally also apply to the Vista Campus.

C Qwaqwa

The situation is receiving attentions and solutions have already been found for most problems.

D General

1. All-inclusive project
A comprehensive investigation into the UFS’s preparedness for and management of long power interruptions will be launched as soon as possible. Available capacity will be utilised first to alleviate the immediate need. The needs assessment to which all faculties and support services have already contributed is already an important building block of the larger project.

2. Building and construction projects currently in the planning and implementation phase
The need for emergency power for projects such as the new Computer Laboratory is being investigated proactively and will be addressed in a suitable manner.

3. Liaison with Centlec
Attempts at direct and continuous liaison are continuing in an attempt to accommodate the unique needs of the UFS.

4. HESA meeting and liaison with other universities
A representative of the UFS will attend a meeting of all higher education institutions on 11 February. The meeting is being arranged by HESA (Higher Education South Africa) to discuss the implications for the sector, the management of risks and the sector’s response to government.

5. Internal communication
It is the intention to communicate internally after every meeting of the task team, which will take place on Mondays. Strategic Communication will assist in this regard.


 