Latest News Archive

Please select Category, Year, and then Month to display items
Years
2019 2020 2021 2024
Previous Archive
28 November 2019 | Story Leonie Bolleurs
Read more new
Dr Sandy-Lynn Steenhuisen and Ruth Cozien at a spot high up in the Maloti-Drakensberg World Heritage Site, close to Sentinel Peak, photographing a Drakensberg crag lizard underneath the leaves of the ‘Hidden Flower’.

Flowers high up in the Maloti-Drakensberg World Heritage Site made world news when it was discovered that the Drakensberg Crag Lizard is their sole pollinator. 

This first for continental Africa – a plant being pollinated by a lizard – is a discovery by a research group including Dr Sandy-Lynn Steenhuisen, Senior Lecturer in the Department of Plant Sciences and affiliate of the Afromontane Research Unit (ARU) at the Qwaqwa Campus of the University of the Free State (UFS), in collaboration with Dr Timo van der Niet, Prof Steven Johnson, and project leader Ruth Cozien, all from the Pollination Ecology Research Laboratory and Centre for Functional Biodiversity at the University of KwaZulu-Natal.

Besides their work being published in popular news here in South Africa (including an isiZulu article), it has also received coverage in, among others, Belgium, Canada, the Netherlands, and the United States of America. 

Is it a bee, a bird, perhaps a mouse?

‘Hidden Flower’, true to its name, is a plant species with flowers hidden at ground level, underneath the leaves of the plant. Like the leaves, the flowers are also green. With the flowers filled with nectar (up to 1 ml per plant) and strongly scented, one concludes that, just as with other flowers, these flowers must be visited by a pollinator. Is it a bee, is it a bird, perhaps a mouse/non-flying mammal?

According to Dr Steenhuisen, who was brought into the project because of her experience with rodents pollinating proteas, many plants are adapted to attract and be pollinated by a specific animal. They attract their pollinators using particular scents and colours and reward them for their service with, for example, nectar, oil, fragrance, and sometimes even shelter. 

The ‘Hidden Flower’ initially had the group of researchers thinking that it was being pollinated by a non-flying mammal. “Everything about the plant made it look like it should be mammal-pollinated,” Dr Steenhuisen said. 

They investigated all options, using several techniques to assess the contribution of different possible animals to set seed. To further assist them in their quest to find the true pollinator, the team put up motion cameras that recorded activity in the area of the ‘Hidden Flower’. 

Great was their surprise when studying the video material after a week of fieldwork in the mountains, finding shy lizards dipping their snouts in the ‘Hidden Flower’ and lapping up the nectar.

Dr Steenhuisen described this discovery as completely bizarre, exciting, and fascinating. 

To make 100% sure that lizards are pollinating the ‘Hidden Flower’, these animals were excluded from the plants. Results published in a paper in Ecology showed that when the lizards were experimentally excluded from the plants, the number of seeds produced dropped dramatically by almost 95%. This finding helped to further prove their discovery. 

Strong scent and bright orange colour attract

The team researched the new phenomenon and found that although flower visitation by lizards is not unknown, it occurs almost exclusively on oceanic islands. Cozien says one should keep in mind that mountains are like sky islands and might therefore have similarities with oceanic islands in terms of their ecology.

The strong scent and the touch of orange at the base of the inside of the flowers is believed to play an important role in attracting lizards. The little lizard may recognise the spots of orange inside the flowers which resemble the orange colour of a male lizard in mating season, attracting females. Lured by the strong scent and the orange spots, the reptiles stick their snouts into the flower in search of nectar, pollinating the ‘Hidden Flower’; thus, making sure that this flower will continue to grow on the slopes of Sentinel Peak in the Maloti Drakensberg range. 

This research finding on lizard pollination, which reads almost like a fairy tale with its islands, hidden flowers, nectar from the gods, and little dragons, shows that there are still many unknown and surprising interactions that need to be discovered and conserved to ensure a healthy ecological system. 

The research findings of this study were published in April 2019. 

News Archive

Power interruptions: Information for internal communication
2008-01-31

As part of the UFS’s commitment to address load shedding, the management would like to communicate the following:

The UFS mainly deals with the power interruptions by way of (a) the possible installation of equipment (e.g. generators) and (b) operational arrangements to ensure the functioning of the UFS in spite of power interruptions.

During the past week progress was made on both fronts. The information that follows resulted from a meeting of a task team of Physical Resources led by Mr Nico Janse van Rensburg, which took place on Monday 28 January (this task team naturally focuses on physical solutions) and a discussion by Exco on Wednesday 30 January 2008. Exco discussed the recommendations of the mentioned task team in respect of physical aspects, as well as the operational arrangements proposed by faculties.

Physical solutions

A Main Campus

1. New emergency power installations already approved:

Last week Exco gave its approval for the design and installation of emergency power equipment in all the large lecture-hall complexes to proceed immediately.

In all these cases

  • load surveys have been completed and a start has been made with the ordering of equipment and the process of appointing contractors. (Exco approved the adjustment of normal tender procedures in an attempt to expedite completion.)
  • generators with 20-30% more capacity than required for the current load are being ordered.
  • provision is being made for the connection of lights and at least one wall plug to the emergency power.
  • the expected construction time is 16 weeks (except in the case of the Flippie Groenewoud Building where it is 6 weeks).

The above-mentioned concerns lecture halls/ venues in the following buildings: Examination Centre, Flippie Groenewoud Building, Stabilis, Genmin and the Agriculture Building.

As far as the Agriculture Building is concerned, a larger generator (larger than required for lecture venues only) is being ordered in view of simultaneously providing essential research equipment (refrigerators, ovens, glasshouses) with emergency power within 16 weeks.

2. Investigation into the optimal utilisation of present emergency power installations

All the emergency power systems are being investigated on the basis of a list compiled in 2006 to determine whether excess capacity is available and whether it is possible to connect additional essential equipment or lights to it.

The electrical engineer warns as follows:
“Staff members must under no circumstances overload present emergency power points.

A typical example of this is a laboratory with 10 power points of which 2 points are emergency power outlets. Normally a fridge and freezer would, for example, be plugged into the two emergency power points, but now, with long load-shedding interruptions, a considerably larger number of appliances are being plugged into the power point by means of multi-sockets and extension cords. In the end the effect of such connections will accumulate at the emergency generator, which will then create a greater danger of it being overloaded and tripping, in other words, no emergency power will then be available.”

3. Requests and needs addressed directly to Physical Resources or reported to Exco via the line managers.

All the physical needs and requests addressed directly to Physical Resources or submitted to Exco via the line managers are being listed, classified and considered technically in view of their being discussed by the task team on Monday 11 February.
The information will (a) lead to recommendations to Exco regarding possible additional urgent emergency power installations, and (b) be used in the comprehensive investigation into the UFS’s preparedness for and management of long power interruptions.

Requests that can easily be complied with immediately and that fit into the general strategy will indeed be dealt with as soon as possible.

4. Purchase of loose-standing equipment: light, small, loose-standing generators, UPSs as solutions to/ aids during power interruptions

Exco approved that

a) faculties and support services accept responsibility themselves for the funding and purchase of loose equipment such as, for example battery lights, should they regard these as essential.
b) UPSs (uninterruptible power supplies) that faculties and support services wish to purchase to combat the detrimental effect of unexpected power interruptions on computer equipment) can (as at present) be purchased from own funds via Computer Services.
c) UPSs (uninterruptible power supplies) that faculties and support services wish to purchase to combat the detrimental effect of unexpected power interruptions on other types of equipment can normally be purchased from own funds with the consent of the line manager concerned.
Note: Please just make sure of the appropriateness of the equipment for a specific situation: it is not a power supply that can bridge a two-hour power interruption.)
d) small, loose-standing generators can be purchased from own funds via Physical Resources and installed under their supervision.
e) laptop computers can , where necessary, be purchased from own budgets. The availability of second-hand laptop computers must be taken into account.

B Vista

No major problems have been reported to date. The situation is being monitored and will be managed according to need. The same guidelines that apply to the Main Campus will naturally also apply to the Vista Campus.

C Qwaqwa

The situation is receiving attentions and solutions have already been found for most problems.

D General

1. All-inclusive project
A comprehensive investigation into the UFS’s preparedness for and management of long power interruptions will be launched as soon as possible. Available capacity will be utilised first to alleviate the immediate need. The needs assessment to which all faculties and support services have already contributed is already an important building block of the larger project.

2. Building and construction projects currently in the planning and implementation phase
The need for emergency power for projects such as the new Computer Laboratory is being investigated proactively and will be addressed in a suitable manner.

3. Liaison with Centlec
Attempts at direct and continuous liaison are continuing in an attempt to accommodate the unique needs of the UFS.

4. HESA meeting and liaison with other universities
A representative of the UFS will attend a meeting of all higher education institutions on 11 February. The meeting is being arranged by HESA (Higher Education South Africa) to discuss the implications for the sector, the management of risks and the sector’s response to government.

5. Internal communication
It is the intention to communicate internally after every meeting of the task team, which will take place on Mondays. Strategic Communication will assist in this regard.


 